| S.No. |
Approval |
Regulatory Authority |
Status |
| 1 |
DPR |
State Government |
DPR for 96 MW approved on 31/07/2008 |
| 2 |
MOU/Implementation Agreement |
State Government |
Agreement signed with Government of Sikkim on 1/03/2006 |
| 3 |
Techno Economic / DPR Clearance from the State Technical Committee |
State Government |
Obtained on 28/11/2008 |
| 4 |
Consent For Establishment (CFE) |
State Pollution Control Board |
CFE under both Air and Water Act is valid upto 31/03/2014 |
| 5 |
Environmental Clearance |
MOEF, GOI/ State Govt. |
Received on 01/04/2008 |
| 6 |
Land Lease Agreement / Status of Land Acquisition |
Government of Sikkim / Private Party |
Full Compensation paid for acquisition of 39 hectares of private land. Approval for diversion of forest land was obtained on 22/02/2010 |
| 7 |
Blasting Permission |
State Government |
The Permanent magazine house license was obtained |
| 8 |
Sales tax |
State Government |
Obtained on 06/04/2009 |
| 9 |
Permission for Power Transmission and Evacuation – Grid interfacing Survey & Estimate |
State Utilities |
Long term Open access obtained |